Concrete Calculator

Concrete for a slab in cubic yards and cubic feet, plus 80 lb and 60 lb bag counts — rounded up, never short.

—

Concrete needed

Volume—
In cubic metres—
80 lb bags (0.6 ft³ each)—
60 lb bags (0.45 ft³ each)—

Note: Bag yields are the standard nominal figures. Add 5–10% for uneven ground and spillage; a slab dug deeper than planned is the usual cause of a shortfall.

Report a problem with this tool

How Much Concrete Does a Slab Really Take?

Volume first: length × width × thickness. A 10 × 10 ft slab at 4 inches thick is 100 × 0.333 = 33.33 cubic feet, which is 1.23 cubic yards — the unit ready-mix trucks sell. In bags, an 80 lb bag yields about 0.6 cubic feet, so the same slab is 56 bags; a 60 lb bag yields 0.45, making it 75. The calculator reports all three so you can price whichever way you are buying.

Worked Example and the Over-Order Rule

Concrete is the worst material to run short on mid-pour — a cold joint is a permanent weakness — and the cheapest to over-order slightly. Add 5–10%: the calculator's bag counts already round up, and ready-mix orders should round to the next quarter yard. Thickness is where estimates quietly die: a slab dug "about 4 inches" that averages 4.5 needs 12% more than the tidy figure. Measure the excavation, not the plan.

Slabs, Footings and Holes

This page is the rectangular slab. The same volume logic extends: a footing is a long thin slab; a post hole is a cylinder (π r² × depth — the Volume Calculator handles it). Whatever the shape, the discipline is identical: honest dimensions in consistent units, volume, then a small deliberate surplus.

Frequently Asked Questions

How many bags of concrete do I need for a 10x10 slab?

At 4 inches thick the slab is 33.33 cubic feet: 56 bags of 80 lb (0.6 cubic feet each) or 75 bags of 60 lb (0.45 each). In ready-mix terms that is 1.23 cubic yards.

How do I convert cubic feet to cubic yards?

Divide by 27. Concrete is ordered in cubic yards from a truck and in bags from a store, and this calculator reports both so the two quotes can be compared.

Should I order extra concrete?

Yes — 5 to 10 percent. Running short mid-pour leaves a cold joint, a permanent weak seam. The usual cause of a shortfall is an excavation deeper than the planned thickness.

What thickness should a slab be?

Four inches suits patios, paths and most garage floors; driveways carrying vehicles often go to 5 or 6. The thickness field drives volume linearly, so test your options here.